Avid readers (!) of this blog will remember a post in June discusing the damage caused to cycle lanes and advance stop line (ASL boxes) by contractors working for the utility companies and the seeming reluctance of Manchester City Council to use their statutory powers to require the contractors to repair the damage. See Digging a hole, don't dig there, dig it elsewhere !
An initial Freedom of Information Act (FoIA) request attempted to find out when the work (damage) had been carried out and by which contractors. After a little bit of to-ing and fro-ing, this FoIA request was answered on 4th July (answers in bold).
"You have requested the following information for the Charles Street / Princess Street junction area:
a) When (date) was the work on the highway,
which resulted in the damage to the Advanced Stop Lines (ASLs), originally
carried out?
The first phase of work was started on 31
January 2010 and completed on 17 February 2011. No defect was recorded.
The second phase of work was carried out
between 12 April to 21 April
b) Which utility company/contractor was
authorised to carry out that work?
The work was carried out by Electricity North
West - Escalon.
Escalon
Ltd, Duncan
Street Yard, Duncan
Street, Salford
M5 3SQ
c) Were the completed road works inspected
by Manchester City Council staff, and if so,
i) on what dates were the inspection(s) undertaken?
No inspection was carried out at the above
site at the time of the opening, as no Random Sample sheets had been generated
by the Exor computer for this site. Note only 10% of each layer of inspection
of all works are generated for inspection by the Exor computer.
ii) What information was recorded as a result of any inspections?
A reported inspection was carried out on
this section of carriageway on 28 June. The information recorded
as a defect was: "no temporary lining" each side
of the cycle bay prior to permanent reinstatement.
iii) What actions, if any, were initiated
as a result of the inspections?
A site meeting has been requested by the inspector with Escalon to discuss the temporary and final reinstatement of the surface and lining."
Only repairing a pothole! |
So what have we learnt from this response? The Department for Transport (DfT) document: Specification for the Reinstatement of Openings in Highways: Second Edition 2002 Section 6.4.5.4 Coloured Surfacings states that : "Coloured surfacings used to highlight highway features such as speed warnings, bus or cycle lanes, ‘gateways’ etc. shall be permanently reinstated using like materials of equivalent type and similar colour.
It is fairly clear that contractors who work on the roads should be required to reinstate the road to how they found it. However, in this case the works were not inspected after completion - despite causing quite major changes in the road surface at a busy junction.
But the good news was that a "defect" had now been recorded and a "site meeting" requested with the contractor, Escalon. So far, so good.
Unfortunately, any progress has been a little more elusive. With no progress on repairs visible by mid October, another FoIA request was submitted. The following response was received on 3rd November (answers embolded):
No comments:
Post a Comment